Airport Construction

Planned Utility Shutdown Request (USR)

John Wayne Airport - Orange County (JWA) planned utility shutdown and return to operational status process applies to all intentional and scheduled shutdowns of Airport Utilities that have the potential to adversely impact multiple JWA Divisions, guests, tenants, and contractors.  Utility Shutdowns are temporary, planned interruptions of service and systems for the safe maintenance, testing, repair, and replacement of equipment or for construction improvements. Utilities affected include, but are not limited to: Power, Water, Gas, Sewer/Waste, Data, Phone, Stormwater/Drainage, and Grease Interceptors.

The USR process is intended to coordinate a scheduled and safe event by notifying all impacted stakeholders, mitigating potential risks and planning for unexpected contingencies, communicating effectively throughout the event, and achieving intended utility levels. Only JWA designated personnel can shut down a utility and schedule shutdowns of Airport Utilities that have the potential to adversely impact multiple JWA Divisions, guests, tenants, and contractors. 

Service Request

ATTENTION: To initiate a service request for a utility deactivation/de-energization, the Requestor must contact their County lease manager, contract manager, or project manager (“JWA Sponsor”) to receive a link to Utility Shutdown Request (USR) Form.

Upon completion of Airport review, the organization requesting the utility shutdown (“Requestor”) must provide a Utility Shutdown Workplan Outline and a Communication Plan.

Laydown Area Request

The purpose of the John Wayne Airport (JWA) Laydown Area Request Form is to be used when requesting the Laydown Area for a construction site where tools, materials, equipment, and vehicles are stored temporarily when they are not in use.  The Laydown Area is to be used for jobs conducted on Airport property.

Laydown Area Request Form must be completed by the Project Manager overseeing the job and must be submitted at least six (6) months in advance to allow the Commercial and Revenue Development Team, Operations Team and Executive Management to review the request in a timely manner. JWA will review the job specifications and determine the highest and best use of Airport space. The advance notice allows the Airport to properly evaluate and accommodate the request while ensuring efficient use of Airport space.

Parking space requests also need to be submitted via Laydown Request Form and the County Project Manager must indicate the parking spaces requested and the dates for use. A separate letter agreement form is attached and will be executed after the approval process.

Instructions

  • Complete the Laydown Area Request Form from the Airport Website.
  • The request must be completed and submitted at least 6 months in advance of the intended use date.
  • The Commercial and Revenue Development Team will coordinate a decision-making committee to discuss the proposed request based on:
    • Job specifications
    • Highest and best use of the Airport space
    • Current business and tenant operation
    • Safety and security
    • Revenue impacts 
    • Schedule
  • The decision-making committee will determine if the request is approved or denied.  Once a decision has been made the Commercial and Revenue Development team will issue an approval or denial response to the requesting Project Manager.
  • Upon approval a Temporary Laydown License will be sent to the Contractor to review, sign and return.  This will finalize the Laydown Area request.
  • The Commercial and Revenue Development Team will maintain a log to keep track of the laydown areas in use.
  • The Commercial and Revenue Development Team will maintain a map of occupied areas and the projected use for the decision-making committee. 
  • No contractor or tenant is authorized to occupy space outside their work area or leasehold without a License Agreement. 
  • Failure to obtain prior approval for any Laydown Area will result in a request to immediately vacate the area at the contractor’s or tenant’s expense.  
     

Go to Laydown Area Request Form