Construction
Stages
JWA’s Improvement
Program is a multi-year
program that includes
the construction of a
new terminal, two new
parking structures and
several updates to the
existing terminal. The
Improvement Program will
be completed in stages
and every effort will
be made to mitigate the
impact on
our passengers and airlines.
Stage 1
- Build new South Remain-Over-Night
(RON) aircraft parking
area
- Stripe area for temporary surface Parking Lot C
 |
 |
Existing
Facilities |
 |
Under Construction |
 |
Construction Complete |
|
Stage 2
- Open surface Parking Lot C and provide free shuttle service between parking area and the Riley Terminal
- Close and demolish B1 Parking Structure
 |
 |
Existing
Facilities |
 |
Under Construction |
 |
Construction Complete |
|
Stage 3
- Begin construction
of new Terminal C
- Construct new 2,000+ space Parking Structure C
- Construct new south commuter/regional
facility
 |
 |
Existing
Facilities |
 |
Under Construction |
 |
Construction Complete |
|
Stage 4
- Open new Terminal C and Parking Structure C
- Close Parking Lot C and relocate aircraft to new South RON
- Construct new C1 parking structure and new north commuter/regional facility
 |
 |
Existing
Facilities |
 |
Under Construction |
 |
Construction Complete |
|