John Wayne Airport has begun construction on one of Orange County’s largest-ever public works projects. The multi-year Airport Improvement Program will add a third Terminal, 2,000+ parking spaces and additional concessions and amenities for our passengers.
What's New
-
Have you seen our ads on OCRegister.com and in the Orange County Business Journal? (May 28, 2008) ... click here to view more ads.
-
The new South Remain-Over-Night (South RON) aircraft parking area, pictured below, will be paved and striped to serve as Temporary Parking Lot C, opening this summer in preparation of the closure of the B1 Parking Structure.

Milestones
The Board of Supervisors recently awarded contracts to:
-
Walker Parking Inc, for Architect/Engineering services for the B1 Parking Structure
-
Excel Paving for construction services of Temporary Parking Lot C
Looking ahead, the Board of Supervisors will award contracts for:
-
Terminal C Commissioning Agent
-
Construction Management services for the B1 Parking Structure