Timeline
JWA’s Improvement Program is a multi-year program that includes the construction of a new terminal, two new parking structures and several updates to the existing terminal.
PROJECT |
2007 |
2008 |
2009 |
2010 |
2011 |
|---|---|---|---|---|---|
South RON |
|||||
Parking Structure B1 Demolition |
|||||
Terminal C |
|||||
Terminal A & B Renovations |
|||||
South Commuter Holdroom |
|||||
North Commuter Holdroom |
|||||
Parking Structure C |
|||||
Central Utility Plant |
|||||
|
Projects and schedules are subject to change |
||||
The
Improvement Program will
be completed in stages
and every effort will
be made to mitigate the
impact on
our passengers and airlines.
Stage 1
- Build new South Remain-Over-Night (RON) aircraft parking area
- Stripe area for temporary surface Parking Lot C
![]() |
|||
|
|
Stage 2
- Open surface Parking Lot C and provide free shuttle service between parking area and the Riley Terminal
- Close and demolish B1 Parking Structure
![]() |
|||
Stage 3
- Begin construction of new Terminal C
- Construct new 2,000+ space Parking Structure C
- Construct new south commuter/regional
facility
![]() |
|||
Stage 4
- Open new Terminal C and Parking Structure C
- Close Parking Lot C and relocate aircraft to new South RON
- Construct new C1 parking structure and new north commuter/regional facility
![]() |
|||